- Progress
- Team successes/needs
- Timing planning
- Blog post, Gantt chart update reminders
- Presentation Planning and
- Future goals
Minutes
Color Notes:
- IJ1 and IJ3 will match "winner" sample part
- IJ2 is Green 2
- TF is white
Summary of team accomplishments:
Team
|
Accomplished
|
To do this week
|
Issues Foreseen
|
IJ1
|
Mold complete
Optimization complete Production run ready - to be scheduled for Tuesday 4/29 from 10-12 |
Production run
|
None
(Help may be needed for production run) |
IJ2
|
Production run complete (110 parts); parts are to spec
Measurements complete |
Help support other teams as best as possible - come in to be backup for production appointments
|
None
|
IJ3
|
Molds complete
|
Process Optimization
Production Run - both will occur Tuesday 4/22 from 3-5 |
Timing - falling a little bit behind and may need help
|
TF
|
Production run complete
|
Parts to be punched
Measure parts |
None
|
Meeting Accomplishments
- Schedule modified for remaining production runs
- Members encouraged to help teams still working to complete part production
- Shims ordered - email sent to Dave
- Production runs completed by 4/29
- Fix Gantt chart again when progress observed after next lab
- Start assembling the top portion in lab on Tuesday 4/29
- "Assembly Party" 4/30 2-6 PM in lab (people can come and go as they are free)
- Presentation preparation
- File in our google drive - to be worked on individually
- Hannah and TBD to present
- Section division of work
- Design: Joanna
- Process Optimization: Jordan
- Process Capability (info to come): Marie
- Lessons Learned (to be discussed upon assembly): Hannah & team
- Each team member