- Begin Assembling TF and IJ2
- Progress
- Assembly Plans
- Blog post, Gantt chart update reminders
- Presentation Planning
- Final goals
Minutes
General Updates
- Shims arrived - fit perfectly!
- Extra appointments canceled
- All final appointments scheduled
Assembly Process:
- Need to turn out inside of sleeves for assembly
- Pull out string from loop side to avoid tangling
- Use pin gauges to check spacing - should standardize spacing
- Made 5 test yoyos
- Decided on 0.022" spacing between the 2 halves (1.5x the string width)
Summary of team accomplishments:
Team
|
Accomplished
|
To do this week
|
Issues Foreseen
|
IJ1
|
Production run complete
Measurements complete |
Assembly!
|
None
|
IJ2
|
Production run complete
Measurements complete |
Assembly!
|
None
|
IJ3
|
Molds complete
Optimization done |
Production Run - both will occur Tuesday 4/29
|
Timing - cutting it close
|
TF
|
Production run complete
Measurements complete |
Assembly!
|
None
|
Meeting Accomplishments
- All TF and IJ2 parts snapped together
- Assembly procedure discussed
- Plans finalized
- Production runs completed by 4/29
- "Assembly Party" 4/30 5-6 PM in lab (all but Joanna and Jordan are free)
- Presentation preparation
- File in our google drive - to be worked on individually
- Hannah and Noa to present
- Section division of work
- Design: Joanna
- Process Optimization: Jordan
- Process Capability (info to come): Marie
- Lessons Learned (to be discussed upon assembly): Hannah & team
- Each team member to contribute to each section individually as needed