Tuesday, April 1, 2014

New Thermoform Mold



The mold for the thermoform part of the yoyo needed to be redesigned because webbing occurred between the protrusions of the pinwheel piece (as seen below).


                Webbing occurred despite many variations in the thermoforming parameters, so it was concluded that a new mold needed to be machined. The new mold was a draw-down mold as opposed to a draping mold. Changing the thermoforming method eliminated all of the webbing in the thermoform part, but jeopardized some of the sharpness of the geometry. The two molds can be seen below (the original mold on the left and the new mold on the right).
 

                When the mold was changed to a draw-down mold, the dimensions of the trapezoids in the mold were increased back to dimensions of the full size part because the size of the pockets was the maximum size of the final part. Shrinkage in the part after forming created clearance for the thermoform part to fit through an injected molded part to be stacked on top of it.


The part was molded in both white and clear 0.03” thick plastic to compare materials. Parameters were optimized so the sharpness of the geometry was not lost due to the change in thermoform method.


The new thermoformed part next to the old thermoformed part.

Body Mold Machining

3/18/14


Pinwheel Yoyo Body Molds







Group Meeting Minutes 4/1

No meeting occurred the week of Spring Break because of group members traveling. Hannah, Joanna, and Kelsey got together to ensure the fit of the IJ2 and TF pieces.

This week's meeting was moved from Friday (typical time) to Tuesday due to group member conflicts.

Agenda

  1. Progress
  2. Team successes/needs
  3. Timing planning
  4. Blog post, Gantt chart update reminders
  5. Future goals

Progress in past week:

  • IJ2 Process Optimization
  • TF Process Optimization (mold remachining required to fix webbing)
  • IJ1 Process Optimization started - molds may need remachining due to issues encountered (too much shrinking)
  • IJ3 molds made - process optimization to occur this week

Summary of team accomplishments:

Team
Accomplished
To do this week
Issues Foreseen
IJ1
         Original molds machined
         Process optimization begun (shrinkage encountered)
          Measure 5 injection molded parts
         Rescale molds in Mastercam, export GCode
        Next week: make new molds, new process optimization
          Shrinkage (being dealt with)
IJ2
         Original molds machined (mold issue fixed with quick remachining of cavity)
         Process optimization completed
         Finish report
         None unless changes need to be made to accommodate other parts
IJ3
         Original molds machined

         Complete process optimization
         Fix any issues with the molds to fit IJ2 and TF, snap fit
         Molds may need changes to fit other parts
TF
         Original molds machined
         New mold machined to fix webbing
         Process optimization completed
         Drill out alignment holes for better center punching (making parts concentric)
         Finish report
         None unless changes need to be made to accommodate other parts

Goals:
  • Complete prototype and Report 3 components by next Friday (4/11) in case any other issues need to be dealt with
  • "Assembly Party" 4/27 (very tentative) or in Tuesday lab

Group Meeting Minutes 3/21 (delayed post)

Our group meeting this week happened remotely due to Spring Break travel plans.

Molds machined:

  • IJ1
  • IJ2
  • TF

To be machined after break:

  • IJ3

To do over break:

  • IJ2 Process Optimization
  • TF Process Optimization
  • Check fit of the two parts
All other team members will be out of town and will finish machining and begin process optimization in the first lab after break (4/1).

Easiest molds to remachine if there are problems:
  • IJ1 (body)
Problems we foresee: IJ3 (cap) may need mold adjustments to fit with other pieces.

We will prioritize not changing IJ2 because of the difficulty of machining.

IJ2 Process Optimization

Justification and Discussion of Process Optimization

At the start of our process optimization, we realized that the 6 trapezoid voids were filled by the mold rather than being hollow as we had expected. This was an error in our original GCode: we mistakenly milled down the cavity too little. However, our original SolidWorks drawings were correct, so this issue did not require a full mold redesign. We fixed the problem by removing an additional 0.02” everywhere on the original cavity but the protruding trapezoids. The new GCode file name is listed below and reflects our finalized mold design.

For the first half of the iterations of injection molding process optimization, machine alignment caused in issue because our part is so thin. The core and cavity did not line up perfectly, resulting in unfilled gaps at the corners of the center triangles. We fixed this by using looser pins to hold the molds in the machine (0.230” brass pins), as suggested by Dave, and manually aligning the core mold slightly back and down in the machine to fix the alignment problem. When we actually run the process to mass-produce parts, we will do several trial runs at the start to ensure correct alignment of the machine. Additionally, we increased the injection hold pressure profile to ensure the whole part would properly fill—the first 5 pressures were changed to 600 psi as shown in our parameter chart below.

Furthermore, the parts from the early runs of our injection molding suffered from flash. The increase in the pressure profile to compensate for voids worsened the initial flash. To fix this, we both decreased the cooling time, cutting it from 12 to 6 seconds, and the feed stroke, decreasing it from 1 to 0.7 inches.  This resulted in a part that met our design specifications in terms of overall appearance and dimensions. 

The original part, with voids and flash, is shown below.


Finally, because our part is so thin, we concluded that we would need to intermittently spray the molds with mold release during the production cycle. Based on our trials, we determined that we should spray the molds every 5 parts.

Once Kelsey, our team member in charge of the thermoformed part that needs to poke through our trapezoid holes, also finished her process optimization, we tested that our parts fit together as designed. The photo below shows our two optimized parts oriented as planned, confirming that both parts are up to specifications.


Component’s Set-up Sheet

INJECTION HOLD
INJECTION HOLD PRESSURE PROFILE: P7-P16
600
600
600
600
600
400
400
350
350
350
INJECTION HOLD TIME
Z2 = 6
COOLING TIME
Z4 = 6
SET SCREW FEED STROKE
C1 = 0.70

INJECTION BOOST
INJECTION SPEED PROFILE: V12 –V21
2
2.5
3
3.5
4
3.5
3
2
1
0.5
INJECTION BOOST PRESSURE
P6 = 1600

SCREW FEEDING
SCREW FEED DELAY TIME
Z3 = 1

EJECTOR
EJECTOR COUNTER
AZ = 2

EJECTOR PIN LENGTH = 5.695”

TOTAL SHIM THICKNESS = 0.037” + 0.007” + 0.010” = 0.054”

- Hannah and Joanna